  9.       
City Council Regular Meeting
Meeting Date: 12/06/2022  

BACKGROUND
City Council previously approved Resolution 22-R-48 to award the landscaping contract to CutRite Landscaping in the amount of $88,172.99 for the Cibolo Valley Median Landscaping Project. A discrepancy was found in the plans versus the field conditions, and additional irrigation pipe, soil, rock, and plants are needed to complete the project.  The contractor has submitted a change order of $16,678.00 for the additional materials needed to complete the project and this resolution increases the contract amount to CutRite Landscaping to a total not to exceed amount of $104,850.99.
GOAL
The goal of the project is to landscape the medians of Cibolo Valley Drive and create the gateway to the Schertz and Cibolo communities.
COMMUNITY BENEFIT
The medians on Cibolo Valley Drive serve as a gateway to both cities - Schertz and Cibolo - and the landscaping needs to reflect the aesthetic expected from our community.
SUMMARY OF RECOMMENDED ACTION
Approve Resolution 22-R-139 authorizing an increase to the contract with CutRite Landscaping for the Cibolo Valley Medians Landscaping Project.
FISCAL IMPACT
The contractor has submitted a change order in the amount of $16,678.00 for the additional materials needed to complete the project and this change order will be funded out of contingency funds.  The new total not to exceed amount is $104,850.99.
RECOMMENDATION
Approve Resolution 22-R-139 authorizing an increase to the contract with CutRite Landscaping for the Cibolo Valley Medians Landscaping Project.
Attachments
Resolution 22-R-139 CVD medians change order
Change Order 1
Original purchase order
original resolution