  9.       
City Council Regular Meeting
Meeting Date: 02/11/2020  

BACKGROUND
Currently, the City of Schertz receives its water supply from Schertz Seguin Local Government Corporation (SSLGC). The water is delivered to our East Live Oak water plant site into our ground storage tanks. It is then pumped into an elevated storage tank on site and out into the distribution system through a bank of pumps. The city is broken into two pressure plains with the dividing line being near Live Oak road. We have one bank of pumps that pump into our northern zone and the other bank of pumps that pump towards the south zone. In the past several years we have begun having pump and motor failures that result in having to pull the pump and/or motors and send them off for repairs.  Depending upon the complexity of the failure, these repairs can take from a few weeks to several months to complete. As our pumping system continues to age, pump failures will continue to occur and as our system grows, multiple pump failures could lead to a situation where we would be unable to appropriately distribute the water supply.
The goal of this project is to construct a redundant pump system to be able to alternate between banks of pumps to limit run time on existing pumps prolonging their life and to provide back-up pumps when maintenance is needed.
Currently, only the engineering design costs have been approved by City Council utilizing the Water and Sewer Fund. Prior to awarding the construction contract, additional funding needs to be approved by City Council to transfer money from the Water and Sewer Reserves into the E. Live Oak Pump Addition Project. 
This project was publicly bid using a Lowest Qualified Bidder Method. The project was bid with a base bid scope of work that included the pumps, piping, electrical equipment, SCADA, and canopy structure and an additive alternate scope of work that included a backup generator and associated generator pad. Four (4) proposals were received for the project.  R.P. Constructors, INC. was the lowest bidder. City Staff evaluated the R.P. Constructors, INC. proposal and found them to be qualified to complete the project based on their experience on other similar projects. R.P. Constructors, INC. proposed to perform the base bid scope of work for $1,272,000.00 and the additive alternate work for $288,000.00. City Staff recommends awarding both scopes of work for a total of $1,560,000.00 as well as a 5% contingency for the project.
GOAL
Approve funding for the E. Live Oak Pump Addition Project.
COMMUNITY BENEFIT
Provide redundant pump capacity to avoid possible interrupted water service caused by pump and motor failures.
SUMMARY OF RECOMMENDED ACTION
Approval of Ordinance 20-T-04 approving the budget adjustment.
FISCAL IMPACT
This ordinance will allocate $1,638,000 to the E. Live Oak Pump Addition Project from the Water and Sewer Reserves. As of September 30, 2019, the Water & Sewer Reserves had an available cash and investment balance for projects of $3,984,869.08. After the transfer, the Water & Sewer Reserves would have $2,346,869.08.
RECOMMENDATION
Approval of First reading Ordinance  No. 20-T-04
Attachments
20-T-04 Budget Adjustment Ordinance